AssetStack response to Eagle Materials: asset baseline, condition capture and maintenance system

AssetStack / Response to Eagle MaterialsSection 01 / 08
01 Executive summary

One asset base for every Eagle plant,
built from the field up.

Response to Eagle Materials Inc.

Asset baseline, condition capture and bottom-up maintenance across eight cement plants and beyond.

AssetStack proposes to give Eagle one consistent asset register, one condition standard and one maintenance strategy method for all eight cement plants, prove it on a single facility with a LiDAR / 3D scan in November, and then extend the same standard to Eagle's wallboard, paperboard, aggregates, concrete and slag operations.

The work starts as an engineering service that builds the asset base. AssetStack is the platform that holds it, so nothing is lost at handover: the register, the evidence and the maintenance plan stay connected and become Eagle's asset and maintenance management system.

Submitted byAssetStack, with SAXUM
DateOctober 2026
Scope8 cement plants first, then 13+ other sites
First milestoneLiDAR pilot, November 2026

Why this is the right tool for the job

  • Standard first, software second. The asset standard is built into the platform, so every plant is structured the same way from day one.
  • Field to plan in one place. Hierarchy, condition, 3D scan and maintenance plan share one asset record, with no re-keying between tools.
  • Bottom-up, not generic. Maintenance tasks come from each asset's own failure modes, criticality and condition.
  • Cement engineering behind it. SAXUM and Lycopodium bring cement process and asset-management experience to the services.
  • Already working. The pilot build is live in this platform today. See it.
Prepared for discussion with Eagle Materials via SAXUM. Response structure follows our understanding of the requirements and will be aligned to Eagle's written requirements summary.ASSETSTACK · 01 / 08
AssetStack / Response to Eagle MaterialsSection 02 / 08
02 Our understanding

What Eagle needs, as we understand it.

From our discussions with Eagle and SAXUM. We will confirm each point against Eagle's asset management requirements summary.

8Major cement plants (wave 1)
13+Wallboard, paperboard, aggregates, concrete and slag sites
~486Cement plant assets in the first baseline (estimate)
1Facility scanned in November

A consistent asset base.

The core problem

Plants acquired and built at different times hold their asset data in different structures and levels of detail. Eagle needs one register that compares like with like across every plant.

What we will deliver

  • Common functional-location coding
  • Shared departments and asset classes
  • Criticality assessed the same way everywhere

Condition you can trust.

Evidence, not opinion

Condition must be captured on one scale, with evidence, so that capital and maintenance decisions across plants rest on the same basis.

What we will deliver

  • 1–5 scale with written criteria
  • Photos and defects per asset
  • LiDAR / 3D context for the pilot facility

Maintenance built from the asset up.

The services opportunity

Eagle is interested in the bottom-up maintenance system development we have delivered for mining clients: strategies derived from failure modes and criticality, not copied from generic schedules.

What we will deliver

  • Failure-mode-based task library
  • Intervals, crafts and hours per plant
  • Templates loaded into the platform
Site list from Eagle Materials' public operations page; plant equipment counts are assumptions until Eagle data is received.ASSETSTACK · 02 / 08
AssetStack / Response to Eagle MaterialsSection 03 / 08
03 Requirements compliance

How each requirement is met.

Every requirement maps to a working screen in the platform, a configuration step, or an engineering service.

RefRequirementHow AssetStack meets itWhereStatus
R1One consistent asset register across all 8 cement plantsSingle functional-location standard (SITE-AREA-CLASS-NN), nine shared cement departments and a common class library applied by template to every plant.Asset hierarchy & standardIn pilot build
R2Extend the same register to wallboard, paperboard, aggregates, concrete and slag sitesLine-specific department sets and classes already defined for each business line; sites carry a rollout wave and status.Portfolio & rolloutIn pilot build
R3Capture asset condition on a consistent basisOne 1–5 condition scale with written criteria, class-specific inspection prompts, photo evidence and full history per asset, usable on phone or tablet.Condition captureIn pilot build
R4Rank assets by consequence of failureA/B/C criticality rules covering safety, environment and production; criticality decides how much maintenance each asset receives.Asset hierarchy & standardIn pilot build
R5LiDAR / 3D scan of a pilot facility linked to the registerScan register, in-app point-cloud viewing for PLY/PCD/XYZ extracts, master E57/LAS files linked from Eagle storage, and scanned equipment tagged to its functional location.LiDAR pilotIn pilot build
R6Bottom-up maintenance system developmentTasks generated from each asset’s class failure modes, filtered by criticality and tightened by condition, with intervals, crafts and annual hours, published as maintenance templates.Bottom-up maintenanceIn pilot build
R7Load existing data from Eagle’s CMMS and spreadsheetsImport and mapping to the standard, with data-steward checks (tag format, class, criticality, orphans, duplicates) before sign-off; CSV load sheet back to the CMMS.Data import · Hierarchy checksConfigure
R8Work management once the baseline is in placeWork orders, maintenance planning, spares, shutdown planning and reliability analytics in the same platform, against the same asset record.Maintenance & work ordersConfigure
R9Field verification and data governance servicesWalkdowns, nameplate capture, criticality workshops and FMEA facilitation by engineers with cement plant experience (SAXUM / Lycopodium).ServicesService
'In pilot build' = working in this platform today with demonstration data. 'Configure' = existing platform capability set up with Eagle's data. 'Service' = delivered by AssetStack and SAXUM engineers.ASSETSTACK · 03 / 08
AssetStack / Response to Eagle MaterialsSection 04 / 08
04 Solution · One asset standard

The same structure at every plant.

The Eagle asset standard is held in the platform and applied by template, so a kiln at Fairborn and a kiln at Nevada are recorded, assessed and maintained the same way.

Functional location convention

FAI-400-KLN-01-GBX

Site · department · asset class · sequence · maintainable component. Applied identically across Eagle's plants and readable by any CMMS.

Nine shared cement departments

100 Quarry & crushing · 200 Raw material storage & prehomogenisation · 300 Raw milling · 400 Pyroprocessing · 500 Clinker cooling & storage · 600 Finish milling · 700 Cement storage, packing & dispatch · 800 Utilities & power distribution · 900 Solid fuel preparation

35 asset classes, 83 failure modes

From crushers and vertical roller mills to kilns, coolers, baghouses and substations, plus classes for wallboard, paperboard, aggregates and ready-mix. Each class says what to inspect and how it fails.

Condition and criticality

1Very goodAs new. No visible defects. Full design function.
2GoodMinor wear or cosmetic defects. No effect on function.
3FairModerate wear, early defects (corrosion, leaks, vibration trending). Function maintained.
4PoorSignificant defects, reduced capacity or reliability. Failure likely within 1–3 years.
5Very poorFailed, unsafe or failure imminent. Function lost or at risk now.

Criticality

  • A · Critical: Full strategy: condition monitoring + preventive + critical spares.
  • B · Important: Preventive and inspection tasks, standard spares.
  • C · Minor: Statutory and lubrication tasks only; run to failure otherwise.
Data steward checks before sign-off

Every load is checked for tag format, a valid class, an assessed criticality, orphans and duplicate tags, so the register stays consistent as more sites join.

Class library aligned to ISO 14224 equipment taxonomy concepts and cement process practice; to be reviewed with Eagle reliability engineers.ASSETSTACK · 04 / 08
AssetStack / Response to Eagle MaterialsSection 05 / 08
05 Solution · November pilot

Prove it on one facility first.

We will scan one Eagle facility with terrestrial LiDAR and 360° imagery, walk down the critical equipment, and build the facility's baseline and maintenance plan inside AssetStack.

Step 1 · By 10 Nov

Prepare

Confirm facility and scope, collect the CMMS extract and drawings, map the existing register to the Eagle standard.

Step 2 · 10–19 Nov

Capture

Terrestrial LiDAR and 360° imagery of the agreed areas; condition walkdown of A and B critical equipment.

Step 3 · By 28 Nov

Build

Register the point cloud, tag scanned equipment to functional locations, generate the facility’s bottom-up maintenance plan.

Step 4 · 4 Dec

Review

Readout with Eagle and SAXUM: verified baseline, findings, and the plan for the remaining seven cement plants.

Scan linked to the register.

Each scanned item carries its functional location and a point-cloud reference, so the 3D view, the register and the condition record open on the same asset.

Deliverables Eagle keeps.

  • Registered point cloud (E57) and 360° imagery
  • Verified hierarchy for the facility
  • Condition scores, defects and photos for A and B assets
  • Bottom-up maintenance plan and CMMS load sheet

A decision at the end.

The readout gives Eagle a measured baseline and a costed plan for the other seven cement plants, so the rollout decision rests on results from one of its own facilities.

Dates are indicative and depend on site access, safety induction and Eagle's choice of facility.ASSETSTACK · 05 / 08
AssetStack / Response to Eagle MaterialsSection 06 / 08
06 Solution · Maintenance and rollout

From baseline to maintenance system.

Once the asset base exists, the maintenance strategy is generated from it, and the same method rolls out site by site.

Bottom-up maintenance

  • Each asset inherits the failure modes of its class.
  • Its criticality decides which failure modes get a task: A gets condition monitoring, preventive work and critical spares; C gets statutory and lubrication tasks only.
  • Poor condition (4–5) halves inspection intervals until the asset is repaired.
  • The result is a task list with intervals, crafts and annual hours per plant, exported to the CMMS or run in AssetStack.
Experience we bring

Criticality and FMEA-based maintenance, CMMS implementation, risk-based inspection, root cause analysis and critical spares, as delivered for mining clients.

Rollout

WaveSitesOutcome
0Pilot facility (November)Method proven, baseline verified
1Remaining seven cement plantsOne register and maintenance strategy for Eagle cement
2American Gypsum wallboard and Republic PaperboardSame standard, line-specific classes
3Aggregates, concrete, slag and terminalsWhole-of-Eagle asset base
RunAll sitesAssetStack retained as the asset and maintenance system
Planned task count is generated from the standard for all eight plants (~1206 recurring tasks) and will change with Eagle's verified equipment lists.ASSETSTACK · 06 / 08
AssetStack / Response to Eagle MaterialsSection 07 / 08
07 Why AssetStack

Engineering experience,
built into the platform.

AssetStack combines an asset platform with the engineering people who know what a cement plant needs from it.

1992Lycopodium established
ASX: LYLListed engineering group
1,400+People across the group*
400+SAXUM projects worldwide*

Cement process understanding.

SAXUM brings cement and lime experience across crushing, grinding, pyroprocessing, materials handling, storage and terminals, which is what the standard and the walkdowns are built on.

One record from field to plan.

Point solutions split the scan, the register, the condition survey and the maintenance plan across tools and consultants. AssetStack keeps them on one asset record, so the services work becomes a system Eagle keeps using.

Open, and Eagle's to keep.

Eagle owns its data. The hierarchy, condition and maintenance plan export to CSV and CMMS load sheets at any time, and the platform connects to existing systems rather than requiring them to be replaced.

For Eagle's IT review

Access
Invited access for the pilot; named user accounts with roles for production use.

Single sign-on
Sign-in with Eagle's identity provider can be configured for production.

Data
Eagle data held in a dedicated application, separate from other clients, with full export.

Audit
Changes to condition and maintenance records keep their history.

Partner experience, not AssetStack deployments. *Scale figures supplied in the capability brief, not a product performance measure.ASSETSTACK · 07 / 08
AssetStack / Response to Eagle MaterialsSection 08 / 08
08 Assumptions & next steps

What we need from Eagle to start.

Assumptions.

  • Eagle nominates the pilot facility and scan areas by early November.
  • Site access, inductions and an escort are provided during capture.
  • An extract of the existing asset register and maintenance plans is available.
  • Kiln and mill counts used in this response are estimates until confirmed.

Exclusions.

  • Changes to Eagle's existing CMMS configuration.
  • Structural or statutory certification arising from the scan.
  • Control-system changes; AssetStack supports decisions and does not control plant.

Next steps.

  • Confirm the pilot facility and dates.
  • Share the asset register extract and drawings.
  • Agree pilot scope and commercial terms.
  • Kick-off call with Eagle, SAXUM and AssetStack.
See the pilot build.The Eagle portfolio, asset standard, condition capture, LiDAR pilot and maintenance builder are working in this platform now.Enter the platform →
Commercial terms for the pilot and the rollout will be provided separately.ASSETSTACK · 08 / 08